DOMElement Object ( [tagName] => img [schemaTypeInfo] => [nodeName] => img [nodeValue] => [nodeType] => 1 [parentNode] => (object value omitted) [childNodes] => (object value omitted) [firstChild] => [lastChild] => [previousSibling] => [attributes] => (object value omitted) [ownerDocument] => (object value omitted) [namespaceURI] => [prefix] => [localName] => img [baseURI] => [textContent] => ) DOMDocument Object ( [doctype] => (object value omitted) [implementation] => (object value omitted) [documentElement] => (object value omitted) [actualEncoding] => [encoding] => [xmlEncoding] => [standalone] => 1 [xmlStandalone] => 1 [version] => [xmlVersion] => [strictErrorChecking] => 1 [documentURI] => [config] => [formatOutput] => [validateOnParse] => [resolveExternals] => [preserveWhiteSpace] => 1 [recover] => [substituteEntities] => [nodeName] => #document [nodeValue] => [nodeType] => 13 [parentNode] => [childNodes] => (object value omitted) [firstChild] => (object value omitted) [lastChild] => (object value omitted) [previousSibling] => [attributes] => [ownerDocument] => [namespaceURI] => [prefix] => [localName] => [baseURI] => [textContent] => V meste aktuálne prebieha oprava výtlkov. Prioritou je najskôr opraviÅ¥ vÅ¡etky veľké a hlboké výtlky z centra smerom na okrajové časti. Harmonogram prác je závislý od aktuálneho počasia. Predpokladáme, že pracovné činnosti budú v rámci technologických možností ukončené v tomto týždni. Práce prebiehajú nasledovne: Streda 19.10. lokalita sídlisko Sever a Cajla Å tvrtok 20.10. lokalita Sever, Cajla a MuÅ¡kát Piatok 21.10. lokalita Čikošňa, sídlisko Juh a Za hradbami Pondelok 24.10. lokalita PažiÅ¥, Grinava Utorok 25.10. Grinava, Polesie, KučiÅ¡dorf Streda 26.10. dokončenie KučiÅ¡dorf Å tvrtok a piatok 28.10. Fajgalská, Leitne, Slnečné údolie Na základe zmluvy k opravám výtlkov a s ňou viazaných finančných prostriedkov budú ďalÅ¡ie práce na oprave výtlkov pokračovaÅ¥ v roku 2023, kedy budú teploty min. 15 stupňov Celzia.   ) DOMElement Object ( [tagName] => img [schemaTypeInfo] => [nodeName] => img [nodeValue] => [nodeType] => 1 [parentNode] => (object value omitted) [childNodes] => (object value omitted) [firstChild] => [lastChild] => [previousSibling] => [attributes] => (object value omitted) [ownerDocument] => (object value omitted) [namespaceURI] => [prefix] => [localName] => img [baseURI] => [textContent] => ) DOMDocument Object ( [doctype] => (object value omitted) [implementation] => (object value omitted) [documentElement] => (object value omitted) [actualEncoding] => [encoding] => [xmlEncoding] => [standalone] => 1 [xmlStandalone] => 1 [version] => [xmlVersion] => [strictErrorChecking] => 1 [documentURI] => [config] => [formatOutput] => [validateOnParse] => [resolveExternals] => [preserveWhiteSpace] => 1 [recover] => [substituteEntities] => [nodeName] => #document [nodeValue] => [nodeType] => 13 [parentNode] => [childNodes] => (object value omitted) [firstChild] => (object value omitted) [lastChild] => (object value omitted) [previousSibling] => [attributes] => [ownerDocument] => [namespaceURI] => [prefix] => [localName] => [baseURI] => [textContent] => V meste aktuálne prebieha oprava výtlkov. Prioritou je najskôr opraviÅ¥ vÅ¡etky veľké a hlboké výtlky z centra smerom na okrajové časti. Harmonogram prác je závislý od aktuálneho počasia. Predpokladáme, že pracovné činnosti budú v rámci technologických možností ukončené v tomto týždni. Práce prebiehajú nasledovne: Streda 19.10. lokalita sídlisko Sever a Cajla Å tvrtok 20.10. lokalita Sever, Cajla a MuÅ¡kát Piatok 21.10. lokalita Čikošňa, sídlisko Juh a Za hradbami Pondelok 24.10. lokalita PažiÅ¥, Grinava Utorok 25.10. Grinava, Polesie, KučiÅ¡dorf Streda 26.10. dokončenie KučiÅ¡dorf Å tvrtok a piatok 28.10. Fajgalská, Leitne, Slnečné údolie Na základe zmluvy k opravám výtlkov a s ňou viazaných finančných prostriedkov budú ďalÅ¡ie práce na oprave výtlkov pokračovaÅ¥ v roku 2023, kedy budú teploty min. 15 stupňov Celzia.   ) Mesto Pezinok | Aktuálne informácie
 


Oprava výtlkov

Táto informácia bola publikovaná od 26. 10. 2022 do 09. 11. 2022

Ilustračné fotoV meste aktuálne prebieha oprava výtlkov. Prioritou je najskôr opraviť všetky veľké a hlboké výtlky z centra smerom na okrajové časti.

Harmonogram prác je závislý od aktuálneho počasia. Predpokladáme, že pracovné činnosti budú v rámci technologických možností ukončené v tomto týždni.

Práce prebiehajú nasledovne:

Streda 19.10. lokalita sídlisko Sever a Cajla

Štvrtok 20.10. lokalita Sever, Cajla a Muškát

Piatok 21.10. lokalita Čikošňa, sídlisko Juh a Za hradbami

Pondelok 24.10. lokalita Pažiť, Grinava

Utorok 25.10. Grinava, Polesie, Kučišdorf

Streda 26.10. dokončenie Kučišdorf

Štvrtok a piatok 28.10. Fajgalská, Leitne, Slnečné údolie

Na základe zmluvy k opravám výtlkov a s ňou viazaných finančných prostriedkov budú ďalšie práce na oprave výtlkov pokračovať v roku 2023, kedy budú teploty min. 15 stupňov Celzia.