DOMElement Object ( [tagName] => img [schemaTypeInfo] => [nodeName] => img [nodeValue] => [nodeType] => 1 [parentNode] => (object value omitted) [childNodes] => (object value omitted) [firstChild] => [lastChild] => [previousSibling] => (object value omitted) [nextSibling] => (object value omitted) [attributes] => (object value omitted) [ownerDocument] => (object value omitted) [namespaceURI] => [prefix] => [localName] => img [baseURI] => [textContent] => ) DOMDocument Object ( [doctype] => (object value omitted) [implementation] => (object value omitted) [documentElement] => (object value omitted) [actualEncoding] => [encoding] => [xmlEncoding] => [standalone] => 1 [xmlStandalone] => 1 [version] => [xmlVersion] => [strictErrorChecking] => 1 [documentURI] => [config] => [formatOutput] => [validateOnParse] => [resolveExternals] => [preserveWhiteSpace] => 1 [recover] => [substituteEntities] => [nodeName] => #document [nodeValue] => [nodeType] => 13 [parentNode] => [childNodes] => (object value omitted) [firstChild] => (object value omitted) [lastChild] => (object value omitted) [previousSibling] => [attributes] => [ownerDocument] => [namespaceURI] => [prefix] => [localName] => [baseURI] => [textContent] => Vo Å¡tvrtok 5. septembra 2013 bol oficiálne odovzdaný Terminál integrovanej dopravy v Pezinku. Pásku slávnostne prestrihol primátor mesta Pezinok Oliver Solga spolu s predsedom BSK Pavlom FreÅ¡om. Terminál integrovanej dopravy v Pezinku (TID) rieÅ¡i celkovú dopravno-obslužnú situáciu v predstaničnom priestore ŽSt. Pezinok. V rámci projektu boli vybudované komunikácie a prísluÅ¡né DZ, chodníky, parkovacie miesta v počte 64 ks, dve kryté odstaviská pre 36 ks bicyklov, verejné osvetlenie s 15 svetelnými bodmi, kamerový bezpečnostný systém s dvoma HD kamerami prepojený na pult Mestskej polície Pezinok, informačný systém cestovných poriadkov, ktorý obsahuje dve centrálne tabule terminálu. Autobusovej doprave budú slúžiÅ¥ aj novovybudované zastávky s piatimi autobusovými prístreÅ¡kami a označovníkmi. Predstaničný priestor dopĺňajú prvky mobiliáru (lavičky, smetné koÅ¡e, zahradzovacie stĺpiky a prvky zelene). Práce začali 1. februára 2013 a ukončené boli 15. augusta 2013. Celková suma na tento projekt bola 428 200€, z toho mesto sa podieľalo 5%, 10% iÅ¡lo zo Å R a 85% prispela EÚ. FOTOGALÉRIA: pred realizáciou TID po realizácii TID ) DOMElement Object ( [tagName] => img [schemaTypeInfo] => [nodeName] => img [nodeValue] => [nodeType] => 1 [parentNode] => (object value omitted) [childNodes] => (object value omitted) [firstChild] => [lastChild] => [previousSibling] => (object value omitted) [nextSibling] => (object value omitted) [attributes] => (object value omitted) [ownerDocument] => (object value omitted) [namespaceURI] => [prefix] => [localName] => img [baseURI] => [textContent] => ) DOMDocument Object ( [doctype] => (object value omitted) [implementation] => (object value omitted) [documentElement] => (object value omitted) [actualEncoding] => [encoding] => [xmlEncoding] => [standalone] => 1 [xmlStandalone] => 1 [version] => [xmlVersion] => [strictErrorChecking] => 1 [documentURI] => [config] => [formatOutput] => [validateOnParse] => [resolveExternals] => [preserveWhiteSpace] => 1 [recover] => [substituteEntities] => [nodeName] => #document [nodeValue] => [nodeType] => 13 [parentNode] => [childNodes] => (object value omitted) [firstChild] => (object value omitted) [lastChild] => (object value omitted) [previousSibling] => [attributes] => [ownerDocument] => [namespaceURI] => [prefix] => [localName] => [baseURI] => [textContent] => Vo Å¡tvrtok 5. septembra 2013 bol oficiálne odovzdaný Terminál integrovanej dopravy v Pezinku. Pásku slávnostne prestrihol primátor mesta Pezinok Oliver Solga spolu s predsedom BSK Pavlom FreÅ¡om. Terminál integrovanej dopravy v Pezinku (TID) rieÅ¡i celkovú dopravno-obslužnú situáciu v predstaničnom priestore ŽSt. Pezinok. V rámci projektu boli vybudované komunikácie a prísluÅ¡né DZ, chodníky, parkovacie miesta v počte 64 ks, dve kryté odstaviská pre 36 ks bicyklov, verejné osvetlenie s 15 svetelnými bodmi, kamerový bezpečnostný systém s dvoma HD kamerami prepojený na pult Mestskej polície Pezinok, informačný systém cestovných poriadkov, ktorý obsahuje dve centrálne tabule terminálu. Autobusovej doprave budú slúžiÅ¥ aj novovybudované zastávky s piatimi autobusovými prístreÅ¡kami a označovníkmi. Predstaničný priestor dopĺňajú prvky mobiliáru (lavičky, smetné koÅ¡e, zahradzovacie stĺpiky a prvky zelene). Práce začali 1. februára 2013 a ukončené boli 15. augusta 2013. Celková suma na tento projekt bola 428 200€, z toho mesto sa podieľalo 5%, 10% iÅ¡lo zo Å R a 85% prispela EÚ. FOTOGALÉRIA: pred realizáciou TID po realizácii TID ) Mesto Pezinok | Aktuálne informácie
 


Dokončená výstavba Terminálu integrovanej dopravy v Pezinku

Táto informácia bola publikovaná od 11. 09. 2013 do 30. 09. 2013

Vo štvrtok 5. septembra 2013 bol oficiálne odovzdaný Terminál integrovanej dopravy v Pezinku. Pásku slávnostne prestrihol primátor mesta Pezinok Oliver Solga spolu s predsedom BSK Pavlom Frešom.

Terminál integrovanej dopravy v Pezinku (TID) rieši celkovú dopravno-obslužnú situáciu v predstaničnom priestore ŽSt. Pezinok. V rámci projektu boli vybudované komunikácie a príslušné DZ, chodníky, parkovacie miesta v počte 64 ks, dve kryté odstaviská pre 36 ks bicyklov, veDokončený Terminál integrovanej dopravy v Pezinkurejné osvetlenie s 15 svetelnými bodmi, kamerový bezpečnostný systém s dvoma HD kamerami prepojený na pult Mestskej polície Pezinok, informačný systém cestovných poriadkov, ktorý obsahuje dve centrálne tabule terminálu. Autobusovej doprave budú slúžiť aj novovybudované zastávky s piatimi autobusovými prístreškami a označovníkmi. Predstaničný priestor dopĺňajú prvky mobiliáru (lavičky, smetné koše, zahradzovacie stĺpiky a prvky zelene).

Práce začali 1. februára 2013 a ukončené boli 15. augusta 2013.
Celková suma na tento projekt bola 428 200€, z toho mesto sa podieľalo 5%, 10% išlo zo ŠR a 85% prispela EÚ.